Course Details
Project Management of Building Constructions 1
Academic Year 2024/25
BVA011 course is part of 1 study plan
BPC-SI / E Winter Semester 4th year
Course Guarantor
Institute
Language of instruction
Czech
Credits
6 credits
Semester
Forms and criteria of assessment
Offered to foreign students
Course on BUT site
Lecture
13 weeks, 2 hours/week, elective
Syllabus
1. Introduction to project management – historic evolution, current conception, suitable use, subject and content, fundamental terms.
2. Project connected with construction, construction as subject of construction project, participants of construction process, construction code.
3. Pre-investment phase of project, initiation, goals setting, documentation, project management, feasibility study.
4. Evaluation of project proposal, planning, structuring of construction project, structuring of construction object.
5. Work organisation of project, construction project participants, organisation structure, ways of construction, personnel provision, project manager.
6. System of construction project planning, types, actualisations and levels of project plans, techniques of project planning, terminal planning.
7. Network analysis, CPM, PERT method, Gantt chart, planning of sources, planning of sources outputs, sources histogram, cost planning, financial planning.
8. Financing of project, proposal prices of project works.
9. Relations between participants in investment project, work contract, command contract, model contract according to FIDIC.
10. Risks and changes management, risks engineering, risks in construction, project risks management.
11. Construction management models, software Microsoft Project.
12. Project controlling, analysis of achieved performance values and progress of project costs, system of progress reporting and cost controlling.
13. Information for construction and civil engineering, termination of lectures.
Exercise
13 weeks, 2 hours/week, compulsory
Syllabus
1. Program of teaching, instruction and guidance. The interpretation and practical examples – Modelling of course of the project, methods and examples of the use of network analysis.
2. Examples of calculation of network graph, reserves and their use.
3. The course of a construction project. Processing flowchart of construction project, correction network graph.
4. 1st task – project definition by method of the logical framework, processing a problem analysis.
5. Continuing work on the 1st task, processing a target analysis and own logical framework.
6. Public presentation of the project definition by method of the logical framework by each group.
7. 2nd task – processing schedule for a specific site in the form of a network diagram, organizational chart, stakeholder responsibility matrix, resource analysis
8. Continuing work on the 2nd task.
9. 3rd task – processing the organogram and functional diagram for particular building.
10. Correction 3rd task.
11. 4th task – Processing and analysing well arranged a schedule of particular building for gross phases of planning and realization, updating and modification of this schedule. The part of this task is processing a costs plan, deployment plan of factual resources and financial plan
12. Continuing work on the 4th task – correction, credit test.
13. Continuing work on the 4th task – correction. Submission of all processed documents in a folder. Credit.