Course Details

Concrete Structures (K)

Academic Year 2025/26

BLA008 course is part of 1 study plan

BPC-SI / K Winter Semester 3rd year

Course Guarantor

Institute

Language of instruction

Czech

Credits

5 credits

Semester

winter

Forms and criteria of assessment

course-unit credit and examination

Offered to foreign students

Not to offer

Course on BUT site

Lecture

13 weeks, 2 hours/week, elective

Syllabus

  • 1.–2. Multi-storey monolithic skeleton constructions – frame structures.
  • 3. Single-storey monolithic frame structures of industrial halls.
  • 4. Dimensioning of reinforced concrete members by limit state of serviceability.
  • 5.–6. Shallow foundations of frame constructions – footings, continuous footings, grids and slabs. Deep foundations.
  • 7. Floor structures edge supported.
  • 8. Floor structures locally supported.
  • 9. Lifted floor structures. Ribbed and cassette slabs. Circular slabs. Simple supported and continuous deep girders.
  • 10. Storage tanks – bunkers and silos.
  • 11. Troughs, tanks and water reservoirs.
  • 12. Channels and ducts. Retaining walls.
  • 13. Precast structures – skeletons, halls, flat and space elements.

Exercise

13 weeks, 2 hours/week, compulsory

Syllabus

  • 1. Cast-in-place RC framed structure - preliminary design of dimensions, scheme of shape of structure, load, loading states for internal frame.
  • 2. Calculation of internal forces of the frame.
  • 3. Calculation of internal forces of the frame - continuation, combination of loads.
  • 4. Dimensioning of cross beam for bend and shear (stirrups, eventually also bends).
  • 5. Curtailment of reinforcement of cross beam. Checking.
  • 6. Dimensioning of one internal column.
  • 7. Structural solution and dimensioning of single footing below internal column.
  • 8. Drawings of reinforcement of the cross beam, single footing and column. Checking.
  • 9. Serviceability limit states – deformation, cracks.
  • 10. Two-way slab – preliminary design, load, internal forces, dimensioning – design of reinforcement.
  • 11. Rebar or netting reinforcing.
  • 12. Final checking.
  • 13. Project submission. Credit.