Project Management of Building Constructions 1
Academic Year 2024/25
BV008 course is not part of any programme in the faculty
Course Guarantor
Institute
Language of instruction
Czech, English
Credits
6 credits
Semester
Forms and criteria of assessment
Offered to foreign students
Course on BUT site
Lecture
13 weeks, 2 hours/week, elective
Syllabus
1. Introduction to project management – historic evolution, current conception, suitable use, subject and content, fundamental terms
2. Project connected with construction, construction as subject of construction project, participants of construction process, construction code
3. Pre-investment phase of project, initiation, goals setting, documentation, project management, feasibility study
4. Evaluation of project proposal, planning, structuring of construction project, structuring of construction object
5. Work organisation of project, construction project participants, organisation structure, ways of construction, personnel provision, project manager
6. System of construction project planning, historic development, types, actualisations and levels of project plans, techniques of project planning, terminal planning
. Network analysis, CPM, PERT method, Gantt chart, planning of sources, planning of sources outputs, sources histogram, cost planning, financial planning
8. Financing of project, proposal prices of project works
9. Relations between participants in investment project, work contract, mandate contract
10. Risks and changes management, risks engineering, risks in construction, project risks management
11. Construction management models, software Microsoft Project
12. Project controlling, analysis of achieved performance values and progress of project costs, system of progress reporting and cost controlling
13. Information for construction and civil engineering, termination of lectures
Exercise
13 weeks, 2 hours/week, compulsory
Syllabus
1. Program of teaching, instruction and guidance. The interpretation and practical examples - Modelling of course of the project, methods and examples of the use of network analysis
2. Examples of calculation of network graph, reserves and their use
3. The course of a construction project. Processing flowchart of construction project, correction network graph
4. 1st task - project definition by method of the logical framework, processing a problem analysis
5. Continuing work on the 1st task, processing a target analysis and own logical framework
6. Public presentation of the project definition by method of the logical framework by each group
7. 2nd task – processing of structural plan for particular building
8. Continuing work on the 2nd task
9. 3rd task – processing the organogram and functional diagram for particular building
10. Correction 3rd task, credit test
11. 4th task - Processing and analysing well arranged a schedule of particular building for gross phases of planning and realization, updating and modification of this schedule. The part of this task is processing a costs plan, deployment plan of factual resources and financial plan
12. Continuing work on the 4th task - correction
13. Continuing work on the 4th task – correction. To submission of all processed documents in an envelope. Credit